Form 8-K
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 8-K
CURRENT REPORT
Pursuant to Section 13 OR 15(d) of The Securities Exchange Act of 1934
Date of Report (Date of earliest event reported): January 10, 2011
FUELCELL ENERGY, INC.
(Exact name of registrant as specified in its charter)
|
|
|
|
|
Delaware
|
|
1-14204
|
|
06-0853042 |
|
|
|
|
|
(State or other jurisdiction
of incorporation)
|
|
(Commission File Number)
|
|
(IRS Employer Identification No.) |
|
|
|
3 Great Pasture Road, Danbury,
Connecticut
|
|
06813 |
|
|
|
(Address of principal executive offices)
|
|
(Zip Code) |
Registrants telephone number, including area code: (203) 825-6000
Not Applicable
(Former name or former address, if changed since last report.)
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:
o |
|
Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425) |
|
o |
|
Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12) |
|
o |
|
Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b)) |
|
o |
|
Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c)) |
Item 1.01 Entry into a Material Definitive Agreement.
On January 10, 2011, FuelCell Energy, Inc. (referred to herein as FuelCell, the Company,
us, we and our) entered into a placement agent agreement with Lazard Capital Markets LLC (the
Placement Agent) relating to a registered direct offering by the Company of up to an aggregate of
10,160,428 units (Units). Each Unit consists of one share of FuelCells common stock and one
warrant to purchase 1.0 share of the Common Stock at a negotiated purchase price of $1.87 per unit.
FuelCell will raise gross proceeds of approximately $19.0 million from the offering of the Units.
The sale of the units is being made pursuant to a subscription agreement between FuelCell and the
sole institutional investor in the offering. The net offering proceeds to the Company from the
sale of the Units, after deducting the Placement Agents fees and other estimated offering expenses
payable by the Company, are expected to be approximately $17.8 million.
The per share exercise price of the warrants is $2.29. The warrant can be exercised
beginning on the date that is six months and one day after the initial closing date and will expire
twenty one months after issuance. In addition, FuelCell will obtain the right, subject to certain
conditions, to require the investor to purchase up to 10.0 million additional shares approximately
nine months post the initial closing date of the transaction. The sale price for the additional
shares will be based on a fixed 10% discount to a VWAP measurement at the time FuelCell exercises
the option. FuelCell cannot require the investor to purchase more than $20 million of additional
shares.
The transaction is expected to close on or about January 13, 2011 subject to customary closing
conditions. A copy of the placement agent agreement, opinion of Robinson & Cole LLP, the form of
subscription agreement and the form of warrant being entered into with the investor are attached to
this Current Report on Form 8-K as Exhibits 1.1, 5.1, 10.1 and 10.2, respectively, and are
incorporated herein by reference. The foregoing is only a brief description of the material terms
of the placement agent agreement, the warrant and the subscription agreement, does not purport to
be a complete description of the rights and obligations of the parties thereunder and such
descriptions are qualified in their entirety by reference to these Exhibits.
The Company offered and is selling the above-described securities pursuant to a prospectus
dated September 21, 2010 and a preliminary prospectus supplement dated January 10, 2011 (the
Prospectus Supplement), pursuant to the Companys shelf registration statement on Form S-3 (SEC
File No. 333-164412), previously declared effective by the Securities and Exchange Commission (the
Shelf Registration Statement). This report on Form 8-K is being filed in part for the purpose of
incorporating Exhibits 1.1, 5.1, 10.1, 10.2 and 99.1 by reference into the Shelf Registration
Statement.
Earlier today, FuelCell issued a press release announcing the above-described offering. A copy
of the press release is attached as Exhibit 99.1 hereto and is incorporated herein by reference.
Item 8.01. Other Events.
This information included in this Current Report on Form 8-K under this Item 8.01 provides a
summary of information with respect to recent developments, which such information has been
disclosed in the Prospectus Supplement. As used herein, all degrees refer to Fahrenheit (F), and
kilowatt and megawatt numbers designate nominal or rated capacity of the referenced power plant. As
used in this prospectus, kilowatt (kW) means 1,000 watts; megawatt (MW) means 1,000,000 watts;
and kilowatt hour (kWh) is equal to 1 kW of power supplied to or taken from an electric circuit
steadily for one hour. All dollar amounts are in U.S. dollars unless otherwise noted.
Recent Developments
2010 Update
Our strategy is focused on continuing to reduce our product costs while expanding in our key
geographic and vertical markets to grow sales volume. We believe that the combination of these two
activities will drive our path to profitability.
We received order flow of 16.4 MW in 2010 which illustrates the growing recognition of the
need for baseload renewable power and the need to use abundant and affordable supplies of natural
gas in the U.S. as cleanly and efficiently as possible. As renewable technologies like wind and
solar are deployed more widely, the need for clean baseload technology that complements these
intermittent sources becomes more acute, particularly baseload power that utilizes renewable
biogas. The ability of DFC Power Plants to utilize renewable biogas to efficiently produce clean
electricity in a reliable manner was a primary driver of order flow during the fourth quarter of
2010. 11.0 MW of the orders received will operate on renewable biogas while the remaining 5.4 MW
will operate on natural gas.
Fuel cells operating on natural gas are attractive for customers that value the clean power
and distributed generation attributes of fuel cells. The virtual lack of pollutants emitted by
fuel cells is important in areas with strict clean air permitting regulations such as certain
regions of California. Providing reliable on-site power generation that reduces reliance on the
transmission grid is also an important attribute of fuel cells that contributed to order activity
in 2010.
During 2010, we received our first direct utility purchase in the U.S. from a major utility in
California. Domestic orders received in 2010 also included two 2.8 MW DFC3000 power plants, which
will be our first installations of this product in the U.S. Prior to these two orders, the DFC3000
had only been sold in South Korea.
For several of these projects, we saw a variety of financing structures used, including
traditional project financing, bonds, grants and tax credits as well as new distribution partners
with their own sources of capital. Our power plant projects typically cost multiple millions of
dollars, have lead times that exceed one year and have project lives that may span five years or
longer. The improved availability of capital was instrumental in closing these orders and
potentially supports future order activity.
The 16.4 MW of orders received during 2010 were concentrated in the second half of the year,
with 12.7 MW received in the fourth quarter. Orders were primarily from U.S. customers in 2010
compared to order activity in 2009 and 2008 that included orders from POSCO Power, which we expect
in 2011. Customers, primarily POSCO Power, ordered 32.8 MW of fuel cells in fiscal 2009 and 32.3
MW in fiscal 2008. We ended fiscal 2010 with 33.5 MW in backlog with 92 percent of the backlog
representing multi-megawatt products, modules and module kits and 8 percent of the backlog
representing sub-megawatt products. Product and service backlog totaled $154.3 million at the end
of 2010, the highest backlog ever achieved. Market updates for the fiscal year were as follows:
Commercial Products
California: Clean energy deployment remains a focus in California with 15.2 MW of orders
received during fiscal 2010. The State and its Public Utilities Commission are driving
clean energy deployment to reduce greenhouse gases and pollution while encouraging the
utilization of distributed generation. Fiscal 2010 California orders will utilize a variety
of fuels, including renewable biogas, directed biogas and natural gas:
|
|
|
6.5 MW of power plants will be located at wastewater treatment
facilities and will utilize renewable biogas for fuel. These orders included a
repeat customer as a municipal water district chose to utilize DFC power plants at
another one of their wastewater treatment plants following an initial purchase in
2007. |
|
|
|
4.5 MW of power plants will operate on directed biogas in San Diego,
California including locations at the University of California, a city-owned pump
station and a wastewater treatment plant. Renewable biogas generated from the
wastewater treatment process will be cleaned and injected into an existing gas
pipeline to fuel the power plants. |
|
|
|
4.2 MW of power plants will operate on natural gas including two
power plants sold to Pacific Gas and Electric, a major utility that will site the
power plants at California universities. A 1.4 MW power plant will be located at a
municipal-owned pump station and will operate on natural gas. The favorable
economic profile of the DFC plant combined with the ability to meet current and
future clean air regulations drove the purchasing decision. |
South Korea: Legislation favorable to fuel cells was passed in March, 2010 by the National
Assembly of the Republic of Korea with the adoption of a Renewable Portfolio Standard (RPS)
requiring 4 percent clean energy generation by 2015 and 10 percent by 2022. Today, only
about one percent of Koreas electricity comes from renewable resources. The South Korean
government desires clean distributed generation power sources to support their growing power
needs while minimizing additional investment and congestion of the transmission grid. Fuel
cells address these needs and are designated as an economic driver due to their ultra-clean
emissions, high efficiency and reliable distributed generation capabilities, which will help
the Country achieve its RPS and electricity generation goals.
The program, which will become effective in 2012, will mandate 350 MW of additional
renewable energy per year through 2016, and 700 megawatts per year through 2022. Carrying
forward the policy introduced in 2006 under Koreas feed-in tariff program, the government
has elected to designate fuel cells operating on natural gas and biogas as New and
Renewable Energy, fully qualifying under the new program.
In response to the new South Korean RPS, POSCO Power began construction of a 100 MW
fuel cell stack assembly plant in South Korea in April 2010 with production expected to
begin in early 2011. For this facility, POSCO Power procured fuel cell stack module
assembly and conditioning equipment through us, which will be used to assemble and condition
fuel cell stacks in South Korea using fuel cell components supplied by us.
In 2010, POSCO Power also ordered a 300 kilowatt DFC 300MA fuel cell power plant to
develop market applications that target grid support combined with the ability to provide
emergency power for installations requiring an uninterrupted supply of power. In the event
of temporary interruption of power from the transmission grid, the fuel cell power plant
would then switch and provide power to the installation. The South Korean Government is
providing financial support for the purchase of this fuel cell power plant and associated
development activities.
We have also partnered with POSCO Power to expand the market for fuel cells in South
Korea through development of a small-scale Direct FuelCell power plant targeted at the
commercial/apartment building market. POSCO Power will fund the development under a joint
development agreement announced subsequent to the fiscal year ended October 31, 2010. The
$5.8 million contract will be funded in stages as performance milestones are reached.
Connecticut: We continue active discussions with private and government financing sources
for the 43.5 MW of fuel cell projects selected and approved by the Connecticut Department of
Utility Control. We also received 0.9 MW of orders in Connecticut during fiscal 2010.
Canada: The highly efficient Direct FuelCell-Energy Recovery Generation (DFC ERG®) power
plant, a joint project with Enbridge Inc., (NYSE: ENB), completed its first year of
operation during 2010. The DFC-ERG plant generated very favorable operating results in the
first year, having attained an average electrical efficiency of 62.5 percent and equipment
up-time of 93 percent. Although its average electrical efficiency of 62.5 percent compares
favorably to a typical conventional fossil fuel generation of about 35 to 40 percent, the
plants peak electrical efficiency topped 70 percent in some of the scenarios under which it
was evaluated. The systems high electrical efficiency allowed it to reduce greenhouse gas
emissions by up to 45 percent compared to a conventional natural gas power plant.
Our first DFC-ERG power plant went into operation in Toronto in 2008 and four DFC-ERG
power plants were approved by the Connecticut Department of Public Utility
Control. The potential market size has been estimated at 250 to 350 MW in just the
Northeastern U.S., northern California and Toronto, Canada.
In September 2009, the Ontario government ruled that gas distribution companies, such
as Enbridge, may own and operate power plants that generate both electricity and heat,
including fuel cells operating on natural gas, up to 10 MW per facility. This is an
essential step toward the deployment of the DFC-ERG for pipeline applications in the
province. The Ontario government is also expected to establish a revised feed-in-tariff to
encourage the installation of clean energy generation that would include stationary fuel
cells.
Government Research and Development Contracts
Advanced Hydrogen Programs:
|
|
|
A DFC300-H2 power plant has been installed at a wastewater treatment
facility in Los Angeles, California to supply 1) hydrogen for use in fuel cell
vehicle refueling, 2) clean electricity, and 3) high quality heat for the
wastewater treatment process. The plant began operating on natural gas during the
fourth quarter of 2010 and is expected to be operational on renewable biogas by
early 2011. The demonstration is being performed under sub-contract to Air
Products with the majority of funding provided by the U.S. Department of Energy
(DOE). |
|
|
|
We were awarded approximately $2.8 million during the fourth quarter
of 2010 by the DOE to demonstrate the hydrogen production capacity of a DFC power
plant for use by the metal processing industry. A DFC300-H2 will be configured to
generate three value streams including: 1) hydrogen for use in a heat treating
process, 2) clean electricity, and 3) high quality heat. Over 600 companies
operate in the metal processing industry in the USA, representing a significant
potential market. |
Hydrogen Compression: We were awarded approximately $2.0 million during the fourth quarter
of 2010 by the DOE to further develop and demonstrate a highly efficient and reliable method
for compressing hydrogen utilizing its solid-state Electrochemical Hydrogen Compressor (EHC)
technology. The EHC technology can be utilized to compress hydrogen for storage, transport
and subsequent use for vehicle refueling or other industrial applications.
Solid Oxide Fuel Cell Development: We continue to partner with Versa Power Systems Inc.
(Versa), for the development of a Large Scale Coal-Based Solid Oxide Fuel Cell under the
U.S. Department of Energy Solid State Energy Conversion Alliance (SECA) Program. The
FuelCell Energy/Versa team met cost and performance objectives for a minimum 25 kW fuel cell
stack in Phase II of the program. The full scale advanced fuel cell system to be
demonstrated in Phase III is expected to incorporate an SOFC module with an output of up to
250 kW to efficiently convert the energy contained in coal to
ultra-clean grid electrical power. We have submitted a bid for approximately $34 million
to the DOE for Phase III and expect a decision in early 2011.
The continued growth in our backlog and our production run rate is a key part of our ongoing
product cost reduction strategy. To date, our cost reduction program has successfully reduced the
unit cost of our megawatt-class products by more than 60 percent. Increased volume enables several
areas of continued cost reduction, including expansion of our global sourcing program, larger
volume purchases, more competition among our suppliers, increased utilization of our factory
capacity, and increased productivity and automation in our facilities and supply chain. As a
result of product cost reductions, sales volume of 75 to 125 MWs will drive the Company to
profitability.
In response to the increased level of domestic orders received in 2010 and anticipating
additional orders from POSCO Power, we increased our production run rate to 35 megawatts per year
during the fourth quarter of fiscal year 2010. We are expecting to continue to ramp the business
to 50 MW and beyond our existing capacity of 70 MW with continued order flow. Actual production in
fiscal 2010 was approximately 22 MW compared to approximately 30 MW in 2009 and approximately 22 MW
in 2008. Our overall manufacturing process (module manufacturing, final assembly, testing and
conditioning) has a production capacity of 70 MW per year.
With increasing order flow, our plan has been to expand production capacity to 150 MW within
our existing Torrington facility. This expansion would require the addition of equipment (e.g.
furnaces, tape casting and other equipment) to increase the capacity of certain operations. Due to
the economies of scale and equipment required, we believe it is more cost effective to add capacity
in large blocks. We estimate that the expansion to 150 MW will require additional capital
investments of $35 to $45 million although, this expansion may occur in stages depending on the
level of market demand.
We also believe that if order flow is slower, we may be able to increase our existing capacity
with lower investment. By investing $5 to $7 million, maximizing existing assets, operating at full
capacity (e.g multiple shifts 24 hours per day) and making other improvements, we estimate that we
can increase capacity from 70 MW to 90 MW of annual production. Depending on product mix, which
would include full power plants, we may be able to reach profitability at 80 to 90 MWs of annual
production.
Backlog
Backlog refers to the aggregate revenues remaining to be earned at a specified date under
contracts we have entered into. Revenue backlog is as follows:
|
|
|
Total product sales and service backlog was $154.3 million at October 31, 2010
compared to $90.7 million as of October 31, 2009. Product order backlog was $87.2 million
and $66.4 million as of October 31, 2010 and 2009, respectively, representing 33.5 MW and
43.7 MW as of October 31, 2010 and October 31, 2009, respectively. Product orders
represent 55 percent of our
total funded backlog as of October 31, 2010. Backlog for long-term service agreements was
$67.1 million and $24.3 million as of October 31, 2010 and 2009, respectively. Although
backlog reflects business that is considered firm, cancellations or scope adjustments may
occur and will be reflected in our backlog when known. |
|
|
|
For research and development contracts, we include the total contract value
including any unfunded portion of the total contract value in backlog. Research and
development contract backlog was $9.7 million and $14.2 million as of October 31, 2010
and 2009, respectively. The unfunded portion of our research and development contracts
amounted to $4.4 million and $10.9 million as of October 31, 2010 and 2009, respectively.
Due to the long-term nature of these contracts, fluctuations from year to year are not an
indication of any future trend. |
As of October 31, 2010 we had contracts for power plants totaling 2.5 MW under PPAs ranging
from five to ten years. Revenue under these agreements is recognized as electricity is produced.
This revenue is not included in backlog described above.
Series 1 Preferred Share Obligation
As previously disclosed, our wholly owned subsidiary (FCE Ltd) had a $12.5 million obligation
originally due to Enbridge on December 31, 2010. The Company and Enbridge have been in negotiations
to modify certain terms of the Series 1 preferred share agreement, and have agreed to extend the
payment deadline to January 31, 2011 to continue these negotiations. Under the existing terms, FCE
Ltd. has the option of meeting this obligation through a cash payment or with unregistered shares
of FuelCell Energy, Inc. common stock. We are a guarantor of FCE Ltds obligations to Enbridge. In
the current negotiations, Enbridge is seeking terms that, as proposed, may require payments in
excess of those we believe we are obligated to pay. While we intend to achieve the most favorable
outcome in light of our obligations under the Series 1 preferred shares, we can not presently
predict the final terms of any agreement with Enbridge.
This obligation relates to dividends accrued on the series 1 preferred stock acquired in the
2003 acquisition of Global Thermoelectric, Inc (GTI). This obligation has been reported in
temporary equity on the balance sheet as redeemable preferred stock of subsidiary. We acquired
Global Thermoelectric due to its expertise in solid oxide fuel cell technology. At the time of the
acquisition, Enbridge owned preferred shares in GTI.
Revolving Credit Facility
In January 2011, we entered into a $5.0 million revolving credit facility with JPMorgan Chase
Bank, N.A. and the Export-Import Bank of the United States. The credit facility is to be used for
working capital to finance the manufacture and production and subsequent export sale of our
products or services. The agreement has a one year term with renewal provisions. The outstanding
principal balance of the facility will bear interest, at our option, of either the one-month LIBOR
plus 1.5 percent or the prime rate of JPMorgan Chase. The facility is secured by certain working
capital assets and general intangibles, up to the amount of the outstanding facility balance.
Item 9.01. Financial Statements and Exhibits.
(d) Exhibits.
|
|
|
|
|
Exhibit No. |
|
Description |
|
|
|
|
|
|
1.1 |
|
|
Placement Agent Agreement, dated January 10, 2011 between
FuelCell Energy, Inc. and Lazard Capital Markets LLC |
|
|
|
|
|
|
5.1 |
|
|
Opinion of Robinson & Cole LLP |
|
|
|
|
|
|
10.1 |
|
|
Form of Subscription Agreement |
|
|
|
|
|
|
10.2 |
|
|
Form of Warrant |
|
|
|
|
|
|
99.1 |
|
|
FuelCell Energy, Inc., Press Release, issued January 10, 2011 |
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly
caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
|
|
|
|
|
|
FUELCELL ENERGY, INC.
|
|
Date: January 10, 2011 |
By: |
/s/ Joseph G. Mahler
|
|
|
|
Joseph G. Mahler |
|
|
|
Senior Vice President, Chief
Financial Officer, Corporate
Secretary and Treasurer |
|
EXHIBIT INDEX
|
|
|
|
|
Exhibit No. |
|
Description |
|
|
|
|
|
|
1.1 |
|
|
Placement Agent Agreement, dated January 10, 2011 between
FuelCell and Lazard Capital Markets LLC |
|
|
|
|
|
|
5.1 |
|
|
Opinion of Robinson & Cole LLP |
|
|
|
|
|
|
10.1 |
|
|
Form of Subscription Agreement |
|
|
|
|
|
|
10.2 |
|
|
Form of Warrant |
|
|
|
|
|
|
99.1 |
|
|
FuelCell Energy, Inc., Press Release, issued January 10, 2011 |