UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
Form 6-K
REPORT OF
FOREIGN PRIVATE ISSUER PURSUANT TO
RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE
ACT OF 1934
For the Month of March 2004
EDP- Electricidadé de Portugal
Praça Marquês de Pombal, 12
1250-162 Lisbon, Portugal
(Address of principal executive offices)
(Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.)
Form 20-F ý Form 40-F o
(Indicate by check mark whether the registrant by
furnishing the information contained in this form
is also thereby furnishing the information to the
Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.)
Yes o No ý
Reuters: EDPP.IN / EDP.N
Bloomberg: EDP PL / EDP US
Investors & Analysts Briefing
INVESTOR RELATIONS DEPARTMENT
Pedro Pires, Director
Gonçalo Santos
Elisabete Ferreira
Cristina Requicha
Rui Antunes
Tel: +351 21 001 2834
Fax: +351 21 001 2899
Email: ir@edp.pt
Site: www.edp.pt
COMMENT ON THE NATIONAL ALLOCATION PLAN OF CARBON EMISSION LICENCES PROPOSAL
The Portuguese Government released yesterday its first proposal of the 2005-2007 National Allocation Plan for CO2 emissions (PNALE), which will be subject to public consultation until the end of March. A final proposal will then be submitted to the European Commissions appreciation and subsequently ratified by the Portuguese Council of Ministers by the 1st of October 2004. Therefore, the figures in the current proposal are preliminary and subject to adjustments.
Yesterdays proposal foresees the attribution of 38,940,517 tonnes of free CO2 emission licences per annum to the industry sectors included in the 2003/87/CE Directive. Without providing any details on the individual licences allocation per thermal plant, this proposal gives the electricity sector 21,500,179 tonnes of CO2 licences per year (already adjusted for the 1.012 factor, in order to account for marginal increases in capacity utilisation in the existing sites).
It is worth mentioning that the 38,940,517 tonnes/year of total licences, but not the 21,500,179 tonnes/year attributed to the electricity sector, include an amount of 1,874,489 tonnes/year to be allocated to new entrants (CO2 emitting facilities, including new thermal power plants such as EDPs TER CCGT, that will start operating from October 2004).
2
The 4th of February 2004 joint proposal made by the main Portuguese electricity generators which suggested the attribution of 24 million tonnes of CO2 licences per year between 2005 and 2007 is not directly comparable with yesterdays proposal made by the Government. The latter includes the islands (Azores and Madeira) emissions and excludes both the hydro volatility risk and the emissions from new power plants:
The PNALE considers 1 million tonnes of CO2 licences per year attributable to electricity generators from the Azores and Madeira islands;
The PNALE assumes an average hydrological regime in the calculation of the licence attributions to the electricity sector, while the proposal made by the Portuguese electricity generators assumed a dryer hydrological regime for the 2005-2007 period. This difference amounts to approximately 2 million tonnes of CO2 per year;
The PNALE set apart, in an item called Reserva Novas Instalações, the emission licenses from new combustion sites that will start operating between October 2004 and the end of 2007. These licenses should partly be attributed to the electricity sector, namely, to TERs second and third generation groups (EDPs new CCGT). Regarding the Portuguese electricity generators proposal, emissions from new thermal power plants were included in the global licensing needs presented to the Government.
The non-consideration of a dry hydrological regime, as proposed by the Portuguese electricity generators, might result in the need of acquiring additional licenses, which would have an impact on the Portuguese electricity systems costs.
The current license attribution proposal already takes into consideration the Electricity sector plan to reduce CO2 emissions by 4.7 million tonnes until 2010 as a result of the voluntary effort to be made by generators in the development of more
EDP - Electricidade de Portugal, S.A. |
Sede: Praça Marquês de Pombal, 12 |
1250-162 Lisboa |
Portugal |
Capital Social: 3,000,000,000 |
Matrícula: 1805 da C.R.C. Lisboa |
Pessoa Colectiva 500 697 256 |
3
environmental-friendly energy sources. EDPs targets on this issue were announced to the market on the 2nd of December 2003 when it presented its Strategy 2006 plan.
The PNALE presented today considers a realistic view on the evolution of CO2 emission that should not compromise the countrys economic convergence towards the European Union average.
EDP ELECTRICIDADE DE PORTUGAL, S.A.
Preliminary proposal for license attribution 2005-2007
Activity |
|
Emissions |
|
Emissions |
|
License |
|
% vs. 2002 |
|
|
|
|
|
|
|
|
|
|
|
Energy |
|
|
|
|
|
|
|
|
|
Thermoelectric power plants |
|
18,508,489 |
|
21,887,725 |
|
21,248,469 |
|
-2.9 |
% |
Refinery |
|
2,549,542 |
|
2,888,988 |
|
3,032,404 |
|
5.0 |
% |
Cogeneration |
|
2,094,427 |
|
2,045,464 |
|
2,462,007 |
|
20.4 |
% |
Other combustion facilities |
|
519,991 |
|
497,821 |
|
565,629 |
|
13.6 |
% |
Steel |
|
649,431 |
|
201,789 |
|
340,587 |
|
68.8 |
% |
Cement and lime |
|
6,619,571 |
|
7,123,561 |
|
7,041,375 |
|
-1.2 |
% |
Glass |
|
622,735 |
|
640,878 |
|
662,063 |
|
3.3 |
% |
Ceramics |
|
847,516 |
|
888,384 |
|
940,103 |
|
5.8 |
% |
Pulp and Paper |
|
471,954 |
|
317,502 |
|
339,447 |
|
6.9 |
% |
S Sectors before adjustment |
|
32,883,656 |
|
36,492,112 |
|
36,632,084 |
|
0.4 |
% |
Adjustment factor |
|
|
|
|
|
1.012 |
|
1.2 |
% |
S Sectors after adjustment |
|
|
|
|
|
37,066,028 |
|
1.6 |
% |
New facilities reserve |
|
|
|
|
|
1,874,489 |
|
5.1 |
% |
Total Licenses |
|
|
|
|
|
38,940,517 |
|
6.7 |
% |
Source: Workgroup |
|
|
|
|
|
|
Unit: ton CO2 |
4
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
Dated March 22, 2004
|
|
|
|
|
EDP- Electricidadé de Portugal |
||
|
|
|
|
|
|
||
|
|
|
|
|
|
||
|
|
|
|
|
By: |
/s/ João Ramalho Talone |
|
|
|
|
|
|
Name: João Ramalho Talone |
||
|
|
|
|
|
Title: Chief Executive Officer |
5